Strategy Analysis

Risk Analysis and Management (Avoid, Transfer, Mitigate, Accept)

Risk analysis and management is a business analysis technique for identifying uncertain events that could affect the value of a change, rating their likelihood and impact, and choosing a response: avoid, transfer, mitigate or accept. Risk analysis and management continues throughout the change, and the organization's risk tolerance shapes which responses are acceptable.

Quick facts

Type
Analysis and planning technique (risk)
Origin
Project and enterprise risk management practice; generic guidance in ISO 31000 (first edition 2009, current edition 2018)
Used when
Comparing options, planning a change, and throughout delivery as conditions change
Main outputs
Risk register: risk, cause, likelihood, impact, rating, owner, response, status
Related techniques
Decision analysis, business case, change strategy, root cause analysis, estimation
Reference
BABOK® Guide v3, §10.38 (Risk Analysis and Management) and §6.3 (Assess Risks)
Exam relevance
One of the 20 techniques named in the ECBA™ blueprint
Risk Analysis and Management (Avoid, Transfer, Mitigate, Accept)Identify risks: with SMEs, for each option or plan. Analyze likelihood and impact: rate each risk on a shared scale. Compare with risk tolerance: which risks need a response. Choose a response: avoid, transfer, mitigate or accept. Assign an owner: one person watches and acts. Monitor and review: new risks, changed ratings, closed risks1Identify risks2Analyze likelihood andimpact3Compare with risktolerance4Choose a response5Assign an owner6Monitor and review

At a glance

  1. Identify risks — with SMEs, for each option or plan
  2. Analyze likelihood and impact — rate each risk on a shared scale
  3. Compare with risk tolerance — which risks need a response
  4. Choose a response — avoid, transfer, mitigate or accept
  5. Assign an owner — one person watches and acts
  6. Monitor and review — new risks, changed ratings, closed risks

What is risk analysis and management in business analysis?

A risk is an uncertain event or condition that, if it occurs, would affect the value a change is meant to deliver. Most risks are threats; some are opportunities, uncertain events that would help.

A risk is not an issue. An issue has already happened and needs handling now; a risk may or may not happen. "The supplier might deliver late" is a risk; "the supplier delivered late" is an issue.

Risk analysis and management is the ongoing cycle of finding risks, judging how likely and how serious each one is, deciding what to do about it and watching it until it closes. Business analysts apply it in two places:

  • When comparing options for a change, because risk is part of each option's value. A cheaper option with a high chance of failure may be worse than a dearer, safer one.
  • When planning and delivering a change, because new risks appear and old ratings change.

Risk analysis and management therefore treats uncertainty as part of the analysis of value, not as a separate project formality.

How do you analyze risks step by step?

At Harbourside Council, permit renewals are moving from paper forms to an online service. The business analyst works with service staff and subject matter experts:

  1. Identify risks early, before options are chosen. Sources include past changes, assumptions and constraints. One risk: some residents, often older ones, cannot use an online service.
  2. Analyze each risk's likelihood and impact on a simple shared scale, such as 1 to 5, and combine them into a rating.
  3. Evaluate each rating against the council's risk tolerance: which risks are acceptable as they are, and which need a response.
  4. Choose a response and an owner. For the access risk: keep a phone-assisted renewal route and a paper form on request.
  5. Record everything in a risk register.
  6. Monitor: review ratings at agreed points, close risks that have passed, and add new ones.
RiskLikelihoodImpactResponseOwner
Residents unable to renew online44Mitigate: assisted phone routeService manager
Payment provider outage at peak24Transfer: service credits in contract; mitigate: grace periodContract manager

Risk analysis and management done this way produces a short, owned list of risks with a planned response for each.

What are the risk responses: avoid, transfer, mitigate and accept?

Four responses are standard for threats:

ResponseWhat it meansExample
AvoidChange the plan so the risk can no longer occurKestrel Retail moves a go-live out of the Christmas peak, so peak disruption cannot happen
TransferShift the impact, usually financial, to another partyA fixed-price contract or insurance
MitigateReduce the likelihood or the impact of a risk that still existsPiloting in two stores before a full rollout
AcceptTake no action to change the risk, but acknowledge it and monitor itA minor reporting delay is logged and reviewed monthly

Two points are often confused:

  • Avoid vs. mitigate. Avoidance removes the risk; mitigation only makes it smaller. If the cause is still there, it is mitigation.
  • Accept vs. ignore. Acceptance is a decision: the risk is recorded, has an owner and is watched.

Transfer has limits: a contract can move financial consequences to a supplier, but not a reputational risk, or the risk that some customers cannot use the solution at all.

For opportunities, the mirror responses commonly used in project risk practice are to exploit, share, enhance or accept them.

The right risk response depends on the rating, the cost of responding and the organization's risk tolerance.

What is risk tolerance?

Risk tolerance describes how much uncertainty an organization, or a stakeholder, is willing to accept in pursuit of value. Three broad attitudes are common:

  • Risk-averse: accepts lower value to reduce uncertainty.
  • Risk-neutral: weighs expected value and uncertainty evenly.
  • Risk-seeking: accepts more uncertainty for a chance of higher value.

Tolerance varies by organization and by topic. At Brightwater Health, tolerance for clinical safety risk is very low: any risk to patients must be avoided or strongly mitigated, even at high cost. The same hospital may be relatively tolerant of risk in a pilot of a new staff rota tool, where failure is cheap and reversible.

Tolerance changes the analysis. The same risk rating may need a response in one context and be acceptable in another. Stakeholders may also differ: a sponsor may be risk-seeking about a deadline while operations staff are risk-averse about service disruption. The analyst makes these differences visible rather than averaging them away.

Risk tolerance is what turns a risk rating into a decision about whether, and how, to respond.

What are the limitations of risk analysis and management?

Risk analysis and management makes uncertainty explicit, supports better comparisons between options and gives owners early warning. Its limits come from how it is practiced:

  • Subjective ratings. Likelihood and impact are often guesses; scales give a false sense of precision.
  • Register theater. A register filled in once and never reviewed provides no protection.
  • Unknown unknowns. Techniques find risks people can imagine; novel situations produce risks nobody listed.
  • Optimism and politics. Teams under pressure underrate risks to their preferred option.
  • Threat focus. Opportunities are rarely analyzed, although they also affect value.

Analysts limit these problems by identifying risks with several stakeholders, using past data where available, reviewing the register at fixed points and treating every rating as provisional.

Risk analysis and management is effective when it is a regular conversation that informs decisions, not a document produced for approval.

Risk analysis vs. root cause analysis: what is the difference?

Risk analysis and managementRoot cause analysis
Time directionLooks forward at what might happenLooks back at what has happened
Starting pointA plan, option or changeA problem or symptom that has occurred
Main outputRisk register with ratings, responses and ownersVerified causes of the problem
Typical questionWhat could go wrong, how likely, how bad, and what will we do?Why did this happen?
LinkLessons from past root causes help identify future risksAn issue that occurred may reveal a risk that was missed

Risk analysis anticipates uncertain events before they happen; root cause analysis explains problems after they appear. Mature teams feed the findings of each into the other.

Exam focus

Risk Analysis and Management (BABOK® Guide §10.38, with Assess Risks at §6.3) is one of the 20 techniques named in the ECBA™ blueprint. Expect definitions of the four responses and scenarios asking when to assess risk. Common traps: confusing avoid with mitigate, treating accept as doing nothing unmonitored, assuming transfer covers every risk, or waiting until an option is chosen before assessing its risks. Practise in the Solution domain drill.

Practise this ECBA™ domain →

FAQ

What are the four risk responses?

The four standard responses to a threat are avoid (change the plan so the risk cannot occur), transfer (shift its impact to another party, such as an insurer or supplier), mitigate (reduce its likelihood or impact) and accept (take no action to change it, but record it, assign an owner and monitor it).

What is the difference between mitigating and avoiding a risk?

Avoiding a risk removes it by changing the plan, so the risk event can no longer happen. Mitigating a risk leaves it in place but lowers its likelihood, its impact or both. If the cause of the risk still exists after the response, the response is mitigation.

What does it mean to accept a risk?

Accepting a risk means deciding not to act to change it, usually because it is minor or a response would cost more than the risk itself. The risk is still recorded, owned and monitored, and a contingency plan may be prepared in case it occurs.

When should a business analyst assess risks?

As early as possible, and certainly before choosing between options, because each option's risks are part of its value. Risk assessment then continues throughout the change: ratings are reviewed, new risks added and closed risks removed. Waiting until after a decision leaves risk out of the decision itself.

What is the difference between a risk and an issue?

A risk is an uncertain event that may happen in the future. An issue is something that has already happened and needs to be dealt with now. When a risk occurs it becomes an issue, and the response moves from planning to action.

What is risk tolerance?

Risk tolerance is the amount of uncertainty an organization or stakeholder is willing to accept to gain value. Risk-averse organizations prefer lower but surer value; risk-seeking ones accept more uncertainty for a chance of greater value. Tolerance decides which risks need a response and which can be accepted.

Sources

Last reviewed

IIBA®, BABOK®, A Guide to the Business Analysis Body of Knowledge®, CBAP® and CCBA® are registered trademarks of International Institute of Business Analysis. ECBA™ and BACCM™ are trademarks of International Institute of Business Analysis. Other names may be trademarks of their respective owners. This guide is independent and is not affiliated with, endorsed by or sponsored by IIBA®. Its practice questions are original and are not taken from any IIBA® exam.