Planning & Monitoring

Stakeholder List, Map and Personas (Power/Interest Grid, Onion, RACI)

Stakeholder list, map and personas is a business analysis technique for identifying who is affected by or can influence a change and analyzing how they relate to it. A stakeholder list names them, a map such as the power/interest grid or onion diagram positions them, a RACI matrix clarifies decision rights, and personas represent large, varied user groups.

Quick facts

Type
Stakeholder analysis technique
Origin
Power/interest grid adapted from Mendelow's power and dynamism framework (1981); onion diagram from Alexander's stakeholder taxonomy (2005); personas from Cooper (1999); RACI from responsibility charts in project management, with no single known originator
Used when
Starting an initiative, planning engagement, or when decision rights or user needs are unclear
Variants
Stakeholder list, power/interest grid, onion diagram, RACI matrix, personas
Related techniques
Organizational modelling, interviews, roles and permissions matrix
Reference
BABOK® Guide v3, §10.43 (Stakeholder List, Map, or Personas)
Exam relevance
One of the 20 techniques named in the ECBA™ blueprint
Stakeholder List, Map and Personas (Power/Interest Grid, Onion, RACI)Manage closely: high power, high interest: involve in decisions. Keep satisfied: high power, low interest: meet their needs without overloading them. Keep informed: low power, high interest: update regularly and listen. Monitor: low power, low interest: watch for shifts with little effort. Power (influence): vertical axis: ability to shape the change. Interest: horizontal axis: how much the change affects or concerns themKeep satisfiedManage closelyMonitorKeep informedInterestPower (influence)

At a glance

  1. Manage closely — high power, high interest: involve in decisions
  2. Keep satisfied — high power, low interest: meet their needs without overloading them
  3. Keep informed — low power, high interest: update regularly and listen
  4. Monitor — low power, low interest: watch for shifts with little effort
  5. Power (influence) — vertical axis: ability to shape the change
  6. Interest — horizontal axis: how much the change affects or concerns them

What are a stakeholder list, a stakeholder map and personas?

They are related tools that answer different questions about the people around a change:

ToolQuestion it answersTypical form
Stakeholder listWho is affected, who influences, who decides?A table with role, interest, influence and contact
Power/interest gridHow much attention does each stakeholder need?A 2×2 grid
Onion diagramHow close is each group to the solution?Concentric rings, from the team outward
RACI matrixWho is responsible, accountable, consulted and informed for each decision or deliverable?A grid of roles against items
PersonasWhat do typical members of a large user group need and do?A short, research-based profile

None of them is an end in itself. They feed stakeholder engagement planning, elicitation and the way the analyst communicates.

Stakeholder lists, maps and personas are therefore lenses on the same people, each chosen for the question at hand.

How do you build a stakeholder list that misses no one?

Most stakeholder lists start with the sponsor and the obvious users. The costly omissions are the groups who do not ask to be involved but can stop or reshape the change late on:

  • control functions: compliance, legal, data protection, internal audit, information security;
  • upstream and downstream teams that send or receive the work;
  • support and operations, who will run the solution;
  • external parties: regulators, suppliers, customers, unions;
  • people whose jobs change, even if they never use the new system.

At Harbourside Council, an analyst listing stakeholders for a new planning-application portal starts with the planning team and the sponsor. Asking "who must approve, who must comply, who receives the output?" adds the legal team, because statutory consultation deadlines apply, and the building-control team, which receives the approved plans.

Good prompts include walking through the process end to end, reading the organization chart, and asking each stakeholder who else should be consulted.

A stakeholder list is complete enough when the groups with direct influence over rules, money or approval are on it.

How do you read a power/interest grid and an onion diagram?

The power/interest grid places each stakeholder by influence over the change (power) and by how much the change concerns them (interest), which suggests how to engage them:

  • High power, high interest: manage closely. Involve them in key decisions.
  • High power, low interest: keep satisfied. Meet their needs and consult them on what matters to them, without flooding them with detail.
  • Low power, high interest: keep informed. Update them regularly and listen; they often know the detail.
  • Low power, low interest: monitor. Check occasionally for changes.

Many analysts add attitude, from supporter to opponent, as a color or a third column, because a powerful opponent needs different handling from a powerful supporter.

The onion diagram shows distance from the solution in rings: the team building it, the people who use it, the wider organization, and the outside world. It is useful for spotting groups beyond the immediate users.

At Larchfield Logistics, the map for a new yard-management system shows the night-shift supervisors, who lost overtime in the last reorganization, as high-interest opponents, and the finance director as a high-power supporter. That combination is a signal to plan engagement with care before elicitation starts.

The grid and the onion are snapshots, so stakeholder maps need redrawing as positions change.

When is a RACI matrix the right tool?

A RACI matrix lists decisions or deliverables against roles and marks each cell:

  • Responsible: does the work;
  • Accountable: owns the outcome and makes the final decision, ideally one role per item;
  • Consulted: gives input before the decision, in a two-way exchange;
  • Informed: is told after the decision.

RACI is the right tool when work stalls because decision rights are unclear. At Kestrel Retail, the e-commerce manager and the store-operations manager each believe they approve the requirements for click-and-collect. Asking both to sign everything builds the deadlock into every approval, and letting whoever answers first decide creates a dispute later. The analyst takes the question to the sponsor, who settles it, and records the result in a RACI matrix so everyone can see it.

RACI is not a stakeholder map: it says nothing about interest, attitude or what users need. Variants add roles such as Supportive or Verifier.

A RACI matrix is therefore most useful for settling and showing who decides, not for understanding stakeholders.

When should you use personas?

Personas are short profiles of fictional but representative users, built from research such as interviews, observation, surveys or data. Each persona has a name, goals, context, frustrations and typical behavior. They stand in for groups too large or varied to involve one by one: customers, citizens, patients.

At Northgate Insurance, an analyst designing a self-service claims journey works with three personas: a first-time claimant who is anxious and unfamiliar with the process, a small-business owner who claims several times a year, and a broker acting on behalf of clients. Requirements and acceptance tests are then checked against each persona: does the journey work for all three?

Personas are useful when the team needs to keep real users in mind. They are weak when they are invented in a meeting without evidence: they then encode the team's assumptions and give them false authority.

Personas are therefore only as good as the research behind them.

What are the limitations of stakeholder lists, maps and personas?

These tools are quick, visual and easy to share, and they make blind spots visible early. Their limits are:

  • Snapshots. Power, interest and attitude change; a map from the first month can mislead by the sixth.
  • Sensitivity. A grid labelling a senior manager "low interest" or "opponent" can offend if it circulates. Many analysts keep a working version private and share a neutral one.
  • Groups hide individuals. "Store staff" may contain supporters and opponents with very different concerns.
  • False precision. Placing a stakeholder on a grid is a judgment, not a measurement.
  • RACI overload. Matrices covering every task are rarely maintained; limit them to decisions and key deliverables.

Stakeholder lists, maps and personas work best when they are kept light, revisited and combined with direct conversation.

Stakeholder map vs. RACI matrix: what is the difference?

Stakeholder map (power/interest, onion)RACI matrix
Question answeredWho matters to this change, and how much attention do they need?Who does, owns, advises on and hears about each decision or deliverable?
Unit of analysisA stakeholder or stakeholder groupA decision or deliverable crossed with a role
Typical usePlanning engagement and communicationSettling decision rights and approvals
Shows attitude?Often, as supporter or opponentNo
Main riskLabels that offend or go staleToo many rows, more than one Accountable role

A stakeholder map shows where people stand; a RACI matrix shows who decides. Analysts often draw the map first, then use RACI for the decisions where rights are disputed or unclear.

Exam focus

Stakeholder List, Map, or Personas (BABOK® Guide §10.43) is one of the 20 techniques named in the ECBA™ blueprint and supports the Stakeholder domain (statements 7.2 and 7.3) and influencing factors in the Change domain (4.1). Expect questions on which stakeholder is missing, which grid quadrant applies, and when to use personas or RACI. Common traps confuse keep satisfied with keep informed, or use RACI to describe user needs. Practise in the Stakeholder domain drill.

Practise this ECBA™ domain →

FAQ

What is a stakeholder map in business analysis?

A stakeholder map is a visual analysis of the people affected by or influencing a change. The most common form is the power/interest grid, which places each stakeholder by influence and interest to suggest how closely to engage them. Onion diagrams show how close each group is to the solution.

How do you manage a stakeholder with high power and low interest?

Keep them satisfied: meet their needs, consult them on the points that matter to them and avoid overloading them with detail. Manage closely is for stakeholders high in both power and interest; keep informed is for those with high interest but little power.

What is the difference between RACI and a stakeholder map?

A stakeholder map analyzes people: their influence, interest and attitude toward the change. A RACI matrix assigns roles for specific decisions or deliverables: who is responsible, accountable, consulted and informed. Use the map to plan engagement and RACI to settle who decides.

When should a business analyst use personas?

Personas are useful when the users are a large, varied group, such as customers or patients, that cannot be involved individually. Each persona summarizes the goals, context and behavior of a typical user type, based on research, so the team can test requirements and designs against them.

Which stakeholders are most often missed?

Control functions such as compliance, legal, audit and data protection; teams upstream and downstream of the process; operations and support teams that will run the solution; and external parties such as regulators and suppliers. They often hold approval rights or rules that reshape the change late on.

Sources

Last reviewed

IIBA®, BABOK®, A Guide to the Business Analysis Body of Knowledge®, CBAP® and CCBA® are registered trademarks of International Institute of Business Analysis. ECBA™ and BACCM™ are trademarks of International Institute of Business Analysis. Other names may be trademarks of their respective owners. This guide is independent and is not affiliated with, endorsed by or sponsored by IIBA®. Its practice questions are original and are not taken from any IIBA® exam.