Process Analysis

Value-Added Analysis (Value-Added, Business-Value-Added and Non-Value-Added Activities)

Value-added analysis is a process analysis technique that classifies each step of a process by whether it creates value for the customer. Steps are usually sorted into value-added, business-value-added and non-value-added activities, and each class gets a different treatment: improve, minimize or eliminate. The time spent in each class shows where flow can improve.

Quick facts

Type
Process analysis technique
Origin
Industrial engineering and the Toyota Production System (Ohno, 1978/1988), Lean Thinking (Womack and Jones, 1996), and business process improvement (Harrington, 1991)
Three classes
Value-added (VA), business-value-added (BVA), non-value-added (NVA)
Key test
Would the customer pay for this step if they could see it?
Related concepts
Lean wastes, value stream mapping, process cycle efficiency, cycle time
Reference
BPM CBOK® v4, knowledge area 3 (Process Analysis)
Exam relevance
CBPP® 2026 blueprint 3.2 Process Analysis Techniques
Value-Added Analysis (Value-Added, Business-Value-Added and Non-Value-Added Activities)Define the customer and output: whose value is being judged, and what they receive. List the steps: from the current-state model, including waits and moves. Classify each step: value-added, business-value-added or non-value-added. Measure time per class: work time and waiting time, not only work. Decide the treatment: improve VA, minimize BVA, eliminate NVA1Define the customer andoutput2List the steps3Classify each step4Measure time per class5Decide the treatment

At a glance

  1. Define the customer and output — whose value is being judged, and what they receive
  2. List the steps — from the current-state model, including waits and moves
  3. Classify each step — value-added, business-value-added or non-value-added
  4. Measure time per class — work time and waiting time, not only work
  5. Decide the treatment — improve VA, minimize BVA, eliminate NVA

What is value-added analysis?

Value-added analysis looks at every step of a process through the eyes of the customer and asks a simple question: does this step make the product or service more valuable to the person who receives it?

The idea comes from manufacturing. The Toyota Production System treated anything that did not transform the product as waste to be removed, and Lean Thinking carried the idea into services and offices. In the business process literature of the early 1990s, including Harrington's work, value-added analysis became a core technique of process improvement. Practice commonly adds a middle class for work that the business needs even though the customer does not value it.

The technique works on a current-state model. Each activity, and ideally each wait and transfer between activities, is classified. The classification is then combined with time data, which shows how much of the elapsed time of a case is spent on work that customers value.

Value-added analysis is therefore a way to see a process as the customer would see it, and to separate the work that matters from the work that only consumes time.

What are value-added, business-value-added and non-value-added activities?

The three classes, with their usual tests and treatments:

ClassTestExamplesTreatment
Value-added (VA)Changes the product or service in a way the customer recognizes and would pay forAssessing a claim, repairing a fault, delivering a parcelKeep and improve
Business-value-added (BVA)Not valued by the customer, but required to run the business: law, regulation, financial control, safetyRegulatory checks, audit trails, tax recordsKeep, but make as lean as possible
Non-value-added (NVA)Neither valued by the customer nor requiredWaiting, re-keying data, searching, rework, unnecessary approvalsEliminate or reduce

Two cases cause most debate. Inspection protects quality but does not change the output, so it is classed as non-value-added or, at best, business-value-added. Regulatory checks are business-value-added: removing them would break the law, so the goal is to make them cheaper and faster, not to drop them.

Some authors use only two classes, VA and NVA, and treat required work as "necessary waste".

Value-added analysis classes are not labels for blame; they decide whether a step should be improved, minimized or removed.

How do you carry out a value-added analysis step by step?

A practical sequence:

  1. Define the customer and the output. Value is judged by the recipient of the process outcome. For internal processes, agree who that is.
  2. List the steps from the current-state model, including waits, transfers and checks, which models often leave out.
  3. Classify each step as VA, BVA or NVA with the people who do the work, recording the reason for each choice.
  4. Measure time per step: work time and elapsed time, using system timestamps where possible.
  5. Calculate the value-added ratio: value-added time divided by total elapsed time, often called process cycle efficiency.
  6. Decide the treatment: remove or shrink NVA steps, simplify BVA steps and improve the flow around VA steps.

The ratio often surprises managers. In most order, service and administrative processes, value-added time is a small fraction of elapsed time; the rest is queues, transport, approvals and rework. That is normal, not a sign that the analysis is wrong, and it points to flow improvement rather than to pushing people to work faster on tasks that already take little of the total time.

A value-added analysis is complete when every step has a class, a time and a decided treatment.

How does value-added analysis relate to the Lean wastes?

Lean practice names the main kinds of non-value-added work, usually as seven wastes, often extended with an eighth for unused human talent, a later addition by Lean practitioners rather than one of Ohno's original seven. They help analysts recognize NVA steps:

WasteIn a service or office process
TransportationMoving files, cases or approvals between people and sites
InventoryCases waiting in queues and inboxes
MotionSearching for information, switching screens and systems
WaitingCases idle until someone is free or a reply arrives
OverproductionProducing reports or documents nobody uses
OverprocessingEntering the same data twice, extra approvals, more detail than needed
DefectsErrors, missing information and the rework they cause

The remedy follows the waste. Duplicate data entry is overprocessing: the fix is to capture the data once and share it, not to make re-keying faster. Waiting usually points to a bottleneck or a handoff, which bottleneck and handoff analysis then explains.

Value-added analysis and the Lean wastes work as a pair: the classification shows how much time is non-value-added, and the wastes name what kind it is.

What does value-added analysis look like in practice?

Harbourside Council renews resident parking permits. A renewal takes six working days from application to permit, and residents complain.

The analyst lists twelve steps with the permits team and classifies them:

  • Value-added: checking eligibility against the address, issuing the permit. Together they take about twenty minutes of work.
  • Business-value-added: recording the payment for audit and keeping a copy of the proof of address, as required by council rules.
  • Non-value-added: printing the online form, re-keying it into the permits system, waiting for a weekly batch approval, and returning incomplete applications by post.

Elapsed time is six days; value-added work is twenty minutes. Most of the delay is the weekly batch approval and the postal loop for incomplete forms.

The permits manager, as process owner, chooses three changes: online forms that cannot be submitted incomplete, direct entry into the permits system and daily approval. The audit steps stay, but are captured automatically.

In practice, value-added analysis turns a vague complaint about slowness into a short list of steps to remove, simplify or protect.

What are the limitations of value-added analysis?

Value-added analysis is simple to explain, quick to apply and focuses attention on the customer and on elapsed time rather than on effort. Its limits are mostly about judgment:

  • Subjective classification. Two teams can classify the same step differently. Recording the reason for each choice and agreeing it with the owner reduces the problem.
  • Who is the customer? For internal and regulatory processes, the "customer" is not obvious, and the classification depends on that choice.
  • Overuse of BVA. Teams protect steps by calling them "required". Ask for the rule or regulation behind each BVA step.
  • It shows what, not why. The analysis finds where time is lost, but root cause analysis is needed to explain why a step exists or why cases wait.
  • Removal risk. Some NVA-looking steps, such as a final check, catch errors created upstream. Remove the cause first, then the check.

Value-added analysis works best as a first screen of a process, followed by deeper techniques where the non-value-added time concentrates.

Value-added analysis vs. value stream mapping: what is the difference?

Value-added analysisValue stream mapping
Unit of analysisEach step of one processThe whole flow of a product or service family, with material and information flows
Main outputA classification of steps (VA, BVA, NVA) and a value-added ratioA current-state and future-state map with inventory, lead time and process time
OriginIndustrial engineering and business process improvementLean practice, popularized by Rother and Shook (1998)
Typical useScreening a process for waste during analysisDesigning a leaner end-to-end flow
RelationshipOften a step inside value stream mappingUses the same value logic on a wider canvas

Value-added analysis classifies steps; value stream mapping draws the whole flow and its delays. Many teams use the first as an input to the second.

Exam focus

Value-added analysis belongs to BPM CBOK® knowledge area 3 and to the CBPP® 2026 blueprint sub-area Process Analysis Techniques (3.2). Expect questions that ask how to classify a step, especially regulatory checks and inspections, how to read a low value-added ratio and which Lean waste a scenario shows. The common trap is labeling a required compliance step as non-value-added and removing it. Practise in the Process Analysis drill.

Practise this CBPP® blueprint area →

FAQ

What is the difference between value-added and non-value-added activities?

A value-added activity changes the product or service in a way the customer recognizes and would pay for, such as assessing a claim or repairing a fault. A non-value-added activity does neither: waiting, re-keying data, searching and rework are typical examples. Value-added steps are improved; non-value-added steps are reduced or removed.

What is a business-value-added activity?

A business-value-added activity is one the customer does not value but the organization must perform, usually because of law, regulation, financial control or safety. A regulatory check is the classic example. The right treatment is to keep it and make it as lean as possible, not to remove it.

What is a good value-added ratio?

There is no universal target, because the ratio depends on the type of process. In most administrative and service processes, value-added time is a small fraction of elapsed time, so a low ratio is common. The useful question is how much waiting and rework can be removed, and how the ratio changes after improvement.

Is inspection a value-added activity?

Usually not. Inspection checks the output but does not change it, so most analysts classify it as non-value-added, or as business-value-added when a rule requires it. The better long-term answer is to remove the causes of the errors that make inspection necessary.

Sources

Last reviewed

CBPP®, CBPA®, CBPL® and BPM CBOK® are registered marks of the Association of Business Process Management Professionals International (ABPMP). Other names may be trademarks of their respective owners. This guide is independent and is not affiliated with, endorsed by or sponsored by ABPMP International or any of its chapters and affiliates, including ABPMP Brasil and France Processus. Its practice questions are original and are not taken from any ABPMP exam.